Tons to Cubic Yards Calculator
Convert tons of gravel into cubic yards instantly. Calculate volume based on material type and density. Supports tons, pounds, kilograms — with cubic yards, cubic feet, and cubic meter output.
Tons to Cubic Yards Conversion Chart
Quick reference for converting tons of gravel to cubic yards across different materials and quantities:
| Material | 1 Ton | 5 Tons | 10 Tons | 15 Tons | 20 Tons |
|---|---|---|---|---|---|
| Crushed Stone | 0.67 yd³ | 3.33 yd³ | 6.67 yd³ | 10.00 yd³ | 13.33 yd³ |
| Gravel | 0.70 yd³ | 3.52 yd³ | 7.04 yd³ | 10.56 yd³ | 14.08 yd³ |
| Sand | 0.74 yd³ | 3.70 yd³ | 7.41 yd³ | 11.11 yd³ | 14.81 yd³ |
| Topsoil | 1.00 yd³ | 5.00 yd³ | 10.00 yd³ | 15.00 yd³ | 20.00 yd³ |
| Mulch | 2.50 yd³ | 12.50 yd³ | 25.00 yd³ | 37.50 yd³ | 50.00 yd³ |
Conversions use standard industry densities. Actual values may vary based on moisture content and compaction.
Material Density Reference
Material density is the key factor in converting tons to cubic yards. Here are the standard densities for common materials:
| Material | Tons / Cubic Yard | Lbs / Cubic Yard | Kg / Cubic Meter | Common Uses |
|---|---|---|---|---|
| Crushed Stone | 1.50 | 3,000 | 1,780 | Driveways, drainage, base material |
| Gravel | 1.42 | 2,840 | 1,685 | Paths, landscaping, general fill |
| Sand | 1.35 | 2,700 | 1,602 | Sandboxes, masonry, bedding |
| Topsoil | 1.00 | 2,000 | 1,187 | Garden beds, lawn preparation |
| Mulch | 0.40 | 800 | 475 | Garden mulch, decorative |
Densities are industry averages. Actual values may vary based on moisture content, compaction, and particle size.
How to Convert Tons to Cubic Yards
Converting tons of gravel to cubic yards is a simple three-step process. Follow this guide or use our calculator above for instant results.
Know Your Gravel Weight in Tons
Determine the total weight of gravel you have or need. If you have pounds, divide by 2,000 to get tons. If you have kilograms, divide by 907.185. For example, 15,000 pounds = 7.5 tons.
Choose the Correct Material Density
Select the density for your material type. Crushed stone = 1.50 tons/yd³, gravel = 1.42 tons/yd³, sand = 1.35 tons/yd³, topsoil = 1.00 tons/yd³, mulch = 0.40 tons/yd³. If you know your supplier's exact density, use that for the most accurate result.
Apply the Conversion Formula
Divide the weight in tons by the material density. The formula is: Cubic Yards = Tons ÷ Density. For example, 15 tons of crushed stone (density 1.50) = 15 ÷ 1.50 = 10.0 cubic yards. To convert to cubic feet, multiply cubic yards by 27.
10 ÷ 1.50 = 6.67 cubic yards
= 180 cubic feet | 5.10 m³
5 ÷ 1.42 = 3.52 cubic yards
= 95 cubic feet | 2.69 m³
Density: 1.35 tons/yd³
4 ÷ 1.35 = 2.96 cubic yards
25 ÷ 1.00 = 25.00 cubic yards
= 675 cubic feet | 19.11 m³
Why Tons and Cubic Yards Are Different
Tons and cubic yards measure two fundamentally different things, which is why a conversion factor (density) is always needed.
Factors That Affect the Conversion
Common Project Conversions
Real-world examples of tons-to-cubic-yards conversions for typical landscaping and construction projects:
Frequently Asked Questions
Related Gravel Tools & Guides
Understanding Tons to Cubic Yards Conversion
If you're planning a gravel project, understanding how to convert tons to cubic yards is one of the most important calculations you'll make. Gravel is typically sold by the ton at quarries and landscape supply yards, but your project dimensions are measured in cubic yards or square feet. This disconnect between how gravel is sold and how projects are measured is where our tons to cubic yards calculator becomes invaluable.
The core formula is straightforward: Cubic Yards = Tons ÷ Density. But the density — measured in tons per cubic yard — varies by material type. Crushed stone is denser (1.50 tons/yd³) than gravel (1.42 tons/yd³), which means 10 tons of crushed stone takes up less space (6.67 cubic yards) than 10 tons of gravel (7.04 cubic yards). Getting this conversion right prevents costly ordering mistakes.
Tips for Accurate Conversion
For the most accurate tons-to-cubic-yards conversion: use the exact density from your gravel supplier rather than generic estimates, account for moisture if the material has been exposed to rain (add 5–10%), and always add 5–10% extra to your order to account for compaction and spillage. A small buffer is far cheaper than a second delivery.